Part: 1 of 4
DUNG QAT ROLL ON

Date:                    March 19-20, 2024

Vessel:                  MV JIN XU XIANG 88

Modules:             PAR 04; PAR 06

Contractor:         ZDJV

Part: 2 of 4
DUNG QAT ROLL ON

Date:                    March 21-22, 2024

Vessel:                  MV JIN XU XIANG 88

Modules:             PAR 05

Contractor:         ZDJV

Part: 3 of 4
DUNG QAT ROLL ON

Date:                    March 23, 2024

Vessel:                  MV JIN XU XIANG 88

Modules:             PAR 03; PAR 09

Contractor:         ZDJV

Part: 4 of 4
DUNG QAT ROLL ON

Date:                    March 24, 2024

Vessel:                  MV JIN XU XIANG 88

Modules:             PAR 07

Contractor:         ZDJV